Measure M: A Summer of Progress + What’s Coming Next

Posted Date: 09/11/26 (03:00 PM)


Logo for Lompoc Unified School District featuring a schoolhouse, bell tower, and floral elements.

Measure M Bond Newsletter

Q3 / 2026

 

Welcome to the 2nd Edition of the Measure M Newsletter

It has been a productive summer for Lompoc Unified School District's Measure M Bond Program. With schools out of session, our construction teams worked across multiple campuses to complete critical health, safety, and infrastructure upgrades — and significant progress has been made. This edition provides a full update on completed summer projects, work currently under contract, and improvements still in planning
 

Measure M at a Glance

A gold background displays four lines of dark blue text detailing voter-approved funding, bond issuance, committed funds, and total projects.
Measure M was passed by Lompoc Unified School District voters in November 2024, authorizing up to $160 million in general obligation bonds for school facility repairs, upgrades, and safety improvements. The District issued its first phase — Measure M Series A — totaling $30 million in 2025, with the planned project window running from June 2025 through April 2028.

Bond funds are focused on the priorities identified by our community and staff:
• Repairing and upgrading classrooms, labs, and career-training facilities
• Improving student safety and campus security systems
• Fixing deteriorating roofs, building envelopes, plumbing, and electrical systems
• Addressing asbestos and other health hazards in aging school buildings
 

Series A Program Status — August 2026

The table below summarizes all six project status categories and current committed values for the Series A program:
A table showing project statuses, costs, and counts, including Complete, Substantially Complete, Contract Awarded, Bidding, Design Phase, and Manzanita Charter School Contribution.

Funding Snapshot

•  $30 million issued in Series A bonds
•  Approximately $22.1 million committed to  projects to date
•  Mandatory independent financial and  performance audits have confirmed that all expenditures are properly accounted for and used only on authorized Measure M projects
 

Recently Completed Summer Projects

The summer break provided the ideal window for construction work that would be disruptive during the school year. With students and staff off campus, contractors worked efficiently across multiple sites to deliver the following completed projects, totally roughly $3,400,000.00 in work done over the summer.

Roofing Replacement & Abatement
New roofs — along with asbestos and hazardous material abatement — were completed at seven school sites, eliminating longstanding safety and maintenance concerns:

  • Vandenberg Middle School  —  $198,459.00
  • Arthur Hapgood Elementary School  —$297,887.00
  • Buena Vista Elementary School  —$788,400.00
  • La Canada Elementary School  —  $985,700.00
  • Lompoc High School  —  $66,360.00
An aerial view shows the gray, flat roofs of long school buildings with an outdoor walkway featuring picnic tables.
An aerial view shows a school campus with a large building featuring a white roof, an adjoining playground, and a parking lot.
New Flooring & Abatement
Some small projects made for a big difference at Fillmore Elementary School Library, and Vandenberg Middle School Science Room

  • Vandenberg Middle School  —$73,485.00
  • Leonora Fillmore Elementary School  —$44,741.00
A well-lit library features tall wooden bookshelves filled with books, grey carpeting, and a comfortable armchair on a raised platform.
Window Replacement & Abatement
Clarence Ruth Elementary School received all new windows for the campus. The projected abated existing hazardous materials at the windows and replaced the older, failing wood windows with modern aluminum windows

Project value: $886,406.00
A long row of glass windows with silver frames is set into the light-colored exterior wall of a building.
A covered walkway runs alongside a light-colored building with large windows and doors.
Exterior Surveillance Cameras
Exterior surveillance camera systems were installed at 8 additional school sites, bringing the total number of sites with upgraded camera coverage to 13! The total cost for all camera system installations to date is $606,716.00

Roofing Repairs & Maintenance
A district-wide roofing repairs and maintenance contract was completed to address minor repairs and extend the lifespan of existing roofing systems across multiple sites.

Project value: $124,008.00

Upcoming Projects

The following projects are actively moving forward — either under awarded contracts or currently out to bid. Work on these projects is expected to begin in the coming weeks and months.

New Restroom Buildings
Contracts have been awarded to build three new restroom facilities for Clarence Ruth ES, Miguelito ES, and Arthur Hapgood ES. The three new facilities are being currently being fabricated by Class Leasing, at their factory in Southern California.  

  • Portable Restroom Purchase  — Clarence Ruth Elementary  ($197,638.00)
  • Portable Restroom Purchase  — Miguelito Elementary  ($200,308.00)
  • Portable Restroom Purchase  — Arthur Hapgood Elementary  ($197,638.00)

Combined value: $595,484.00

The architectural drawings for the foundation and utilities for these three site are in process with the District’s architect. When complete, we will go out to bid for the construction and installation phases of these new facilities, with the goal for completion end of Summer 2027.

Out to Bid — Awaiting Award
The following projects are currently out for competitive bid. Contract awards are anticipated in the coming weeks, and will be completed during the next school year.

  • Storefront Window Replacement Pilot Project — Cabrillo High School   ($90,000.00)
  • IP / Public Address System Modernization — Vandenberg Middle School ($750,000.00)
 

Projects on the Drawing Board (Design Phase)

The following projects are a sampling of work currently in the design and planning phase. Architects, engineers, and District staff are working to develop plans, obtain permits, and prepare bid documents. These projects represent the next wave of improvements for our school sites.

Window Replacement & Abatement — Multiple Sites
Window replacement projects prioritize removal of aging single-pane and deteriorating storefront windows and replacement with modern, energy-efficient systems — addressing both health and energy goals identified in the Measure M plan. We currently have approved plans for Leonora Fillmore Elementary School and Arthur Hapgood Elementary School. At the completion of the Cabrillo HS Pilot Project, we will begin to develop plans to replace the window/storefront systems at both Cabrillo HS and Lompoc HS.  

Estimated value: Cost estimate pending (TBD)

Gas and Water Piping Replacement — Multiple Sites
Design is underway for the replacement of aging gas and water infrastructure across multiple school sites. This project addresses one of the top infrastructure priorities identified in the District's 2025 staff survey and Facility Master Plan.

Estimated value: Cost estimate pending (TBD)

Exterior Painting Projects — All Sites
A district-wide exterior painting program is in design, covering all school sites. Fresh exterior paint improves the appearance of campuses and provides protective coating for aging building surfaces.

Estimated value: Cost estimate pending (TBD)

Classroom Ceiling Tile Replacement / Abatement — Multiple Sites
Design work is beginning for the replacement of aging classroom ceiling tiles, which in many cases contain asbestos. This project was the highest-ranked priority in the March 2025 staff survey, with 190 staff responses.

Estimated value: Cost estimate pending (TBD)

Asphalt Plan & Projects — Multiple Sites
The District is developing a comprehensive asphalt repair and replacement plan for parking lots, driveways, and play areas across multiple sites.

Estimated value: Cost estimate pending (TBD)

Stay Connected

This is the 2nd edition of the Measure M Newsletter. We are committed to keeping our community informed and engaged throughout the life of the bond program. Future editions will include:

  • Project completion updates with photos
  • Upcoming construction timelines and campus access information
  • Planning updates for Series B and future bond phases
  • Opportunities for community input

Have questions about Measure M projects? Contact Bond Project Manager Jon Bruenning directly: